It’s been a month since we did an update on the reconstruction of the Wildwood Boardwalk.
Let’s go ahead and revisit this project and give you an updated tour. [You can see the tour at the bottom of this article]
Wildwood Boardwalk Reconstruction Update – April 2022
For those who don’t know, the city of Wildwood is working on a multi-year project which will see the reconstruction of most of the Wildwood Boardwalk.
This project is projected to cost 25 Million and will be broken up into different phases
The first phases of the project included the streets between Oak and Maple Avenues.
Over the past few months contractors ripped up the old boardwalk, removed the tramcar pathways, fixed up the existing concrete, and laid the first layer of wood on top.
Currently, they are installing the new 2x4s on top and making a new pattern on the boardwalk.
This project is running on schedule with a completion date of mid-May, but there is a bit of a change.
The original wood that the city was using for the project was delayed and wouldn’t be here until mid-April.
Instead, the city changed to Pine so that the project will finish as scheduled.
The other wood will come in and will be used for the next section of the project.
Below is our video update on the Wildwood Boardwalk.
Before you watch please consider subscribing to our YouTube channel
A Special Thank You to our Patrons on Our Patreon page. If you would like to become a patron and support this channel, click HERE.
Check out these other Wildwood videos and articles.